10 Signs that Your Team Isn’t Really Agile
Sunday, January 22, 2012
How to Use Agile Estimation in Scrum Projects
Like it or not, estimations are a big part of professional and commercial software development. Estimations are used in most projects regardless of methodology: Waterfall or Scrum, traditional or agile, every stakeholder needs to know the numbers. Projects succeed or fail as a result of these. Unfortunately, humans, as a rule, tend to suck at estimating.
This post will compare and contrast the different estimation techniques and applications used by both agile and non-agile methodologies, and explain how to use them (and not misuse them), particularly in a Scrum project.
What is Wrong with how We Estimate?
Traditional project plans involve using calendric estimates in order to synchronize the development efforts of the team(s) by placing the work on a time line (usually, using a Gantt chart). This means that for every part of the solution, the developers must predict the when it will be ready (i.e. the delivery date). This means they need to know when they will start, how much time it will take to deliver the work, and how much time will be “wasted” on impediments (both foreseeable and unforeseeable). While knowing this makes the project planners’ work easier, obtaining this knowledge is extremely difficult; Estimating the development effort is difficult enough, but predicting the total amount of time that will be spent not developing is near impossible.
What’s worse, is that contrary to popular belief, the Law of Large Numbers does not apply to project plans! Due to the nature of dependencies, a single late dependency is enough to push the delivery date of a dependent component. On the other hand, in order for a component to be delivered early, it is necessary that all dependencies will be completed early. In short, lateness aggregates, while earliness does not.
A side effect of this is that the more complex the Gantt based project is, the more lateness is likely to be accumulated, as the project advances, and the further we are in the project, the more we run the risk of being late.
Of course, a late project means that the software is delivered at a higher cost, with less features, and / or simply later than expected and agreed. This means that a late project often becomes a failed project.
Clearly, a different method of doing things is necessary; Agile methodologists came up with different estimation techniques to reduce the chances and ramifications of failure.
Agile Estimations Are Easier to Make
The three most common agile estimations are T-Shirt Sizes, Ideal Time, and Story Points:
- T-Shirt Size estimations are coarse grained separation of requirements into buckets of small, medium, large, or very-large efforts. This estimate is of course extremely easy to make intuitively, and of course insufficient as a basis for project planning due to its low resolution, but is often sufficient for the purpose of pricing single features (example scenario might be when required to give a customer a cost estimate for some custom feature in the system).
- Ideal Time estimates are similar to calendric estimates in that they involve high resolution predictions of the effort involved in developing a feature. The difference is that ideal estimates are made while ignoring all surprises and interferences! The question that ideal estimates answer is “how much time will it take to develop a solution, assuming you work on nothing else, and nothing else disturbs you”. Taking the unknowable impediment factor out of the equation improves the accuracy of the estimates, but you can’t simply substitute ideal time for calendric time because the unknown impediments still do exist, and the fact remains that humans aren’t good at making absolute estimates, with no point of reference. In Scrum, Ideal Hours are often used to estimate the effort of completing tasks, which should be short, simple and straightforward.
- Story Points are a radically different method of estimating development effort. With story points you do not go out and say how much work something is, in and of itself, but rather state how the effort to develop one component compares to the effort of developing another. These estimates are much easier to make, and surprisingly accurate because we are much better at comparing things than estimating them. Of course, comparisons and relationships have no unit of measure, and thus can’t be used to establish a timeline. At least not in the normal sense. In Scrum, Story Points are usually used to estimate the effort of completing user stories (hence the name).
Agile Estimation Techniques Make Better Plans
While agile estimation techniques tend to end up more accurate than calendric estimates, the estimations are still guesses, and guesses still mean risk. Agile teams try to reduce this risk by reducing the amount of guesswork involved in the project plan.
Classic project plans involve estimating the time it will take to deliver each component, and add up all the estimates to create one big guess-of-a-plan. While agile project plans involve estimating the work on each component as well, that is where the similarity ends.
The agile project plan is not based on the prediction of work effort, but rather on empirical evidence! Only the team’s first iteration (ever) is planned based on a prediction. The rest are based on the measured evidence of previous iterations (or sprints, as they are often called in Scrum-shops). The team estimates that it will successfully complete as much work in the next iteration as it did in the previous iteration(s).
For example, if a team successfully completed 120 ideal hours worth of work (that is, the amount of work they did added up to what they estimated as 120 ideal hours), then they will estimate that they will do the same in the next iteration. This technique works the same with story points: A team that can complete an average of 50 story points in an iteration is likely to repeat that success in the next one. A team’s velocity, or cadence can then be measured in ideal hours per iteration or story points per sprint.
What about interruptions? Well here’s the beauty of the technique: You can consistently account for the predictable ones (e.g. vacations, repeat meetings, scheduled events) and factor those out, and you can consistently ignore the unplanned ones, as they are likely to be more or less an equal part of every iteration of the team.
Where’s the Difference?
The difference between predictive plans (classic, waterfall-ish, Gantt based) and empirical plans (Agile, Scrum) are:
- Predictive plans are based on more estimation (i.e. guesses, i.e. risk) than empirical ones
- Empirical plans have an increasingly sound statistical ground as the project progresses
- Predictive plans have an increasing chance of running late, as the project progresses
- With predictive plans the unknown factors aggregate, with empirical plans they cancel each other out.
Finally, as stated in the previous post, agile plans, being based on stories that are designed to be discrete units of business-value, with as little interdependencies as possible, agile plans further mitigate the risk of estimation failure by causing the ramification to be failure to deliver on time only the least valuable features!
In Conclusion
To me, the agile choice is a no brainer. Agile plans are simply safer to execute, the chance of failure is lesser, and the result is less harmful. I would even go as far as to say that companies promising to deliver a non-trivial project without using an agile plan of some sorts are being less than honest – with themselves as well as the customer.
Moreover, I think it is high time that customers demand their contractors to use agile methods in order to win contracts.
Thursday, January 5, 2012
Demystifying Agile: How to Plan Releases with Scrum
The agile release process might sometimes seem like voodoo (or even dark voodoo) to some managers and developers, particularly those more accustomed to the traditional way of planning processes used in waterfall projects. This post will explain the inherent problems with waterfall projects, how agile methodologies such as Scrum overcome these problems, and of course, the reasons that the agile release planning method works.
You Can’t Control Everything
The PMBOK call it the project management triangle; the agile community call it the Iron Triangle. Regardless of the name, it is a real and hard constraint: Of the three aspects of the project – scope, resources (or cost), and time you may pick and control any two. The third cannot be controlled without harming the quality, and is calculated (roughly) by the following formula:
This means that if you have a project where the budget is fixed, and there is a hard deadline (i.e. release date), then you cannot control the scope that will be delivered by the team by the time of the release.
Moreover, Brook’s Law, states that adding people to a late (i.e. already started) project will only make it later. According to this, since the cost of a software project is mostly the cost of the team members, the resources must remain fixed for the project (or release).
Nevertheless, traditional project managers seem to try to define the entire scope of a project, define the releases and milestones (i.e. the time), with a fixed preset budget (i.e. cost).
It is simply doomed to fail. According to the Standish Group and the Chaos Report, most projects (68 percent) do.
Why do Projects Fail?
According to Martin Fowler, it is not the projects that fail, but rather the estimates that fail; it is our attempt to calculate how much time it will take to deliver a certain scope with a certain amount of resources.
I would argue, that the failure to estimate is the reason that projects fail. We really don’t know how to estimate. Projects fail because they rely too heavily on the estimates.
How do Agile Methods Reconcile with the Iron Triangle?
Given values such as courage and honesty, it is no surprise that agile methodologists simply acknowledge that estimation is not a good basis for a release plan, and search for alternatives.
Given the Iron Triangle, Brook’s Law, and the fact that most customers demand a hard release date, an agile PM accepts that he cannot control the scope that will be delivered; that is, while the PM may make guesses (i.e. estimates) as to the content that will be delivered on the deadline, he cannot be sure that every last task will be completed.
What he can promise, and make certain of, is that he will deliver the best product possible on the release date, with the rest of the desired features in consecutive releases.
How do Agile Methods Deliver the Best Product on Time?
By slicing the entire scope into vertical slices, small increments in valuable functionality (often called user stories), the agile PM now has a stack of user stories to be released, or a product backlog. By defining the stories in such a way that they have as few interdependencies as possible, the PM may order them as he desires. The PM will of course, choose to order them by business value to the customer.
The development team, in turn, will swarm on each story, by order of value (priority), and focus on completely delivering one story at a time (completely means coding, testing, integrating and anything else required).
In this way, at any given moment, including the release date, the team has a product that is shippable and is the most valuable product they could possibly develop.
Is the Best Product Possible Good Enough?
While the best product might not be everything that was envisioned, because again – that is simply not possible: not with waterfall, not with agile, not anyway – the “Best Product” will have the capabilities most valued by the customer.
The findings of the Standish Group show that only 20% of the features in any given product are frequently used, while 64% are rarely or never used. Therefore, statistically speaking, even if you only complete 36% of your scope, you may still have a good enough product!
Of course, assuming that you aren’t slacking, and the project’s deadline isn’t insanely short, it is more likely that you will complete a significantly larger portion of your scope. It is even possible that you will have a “good enough” product that you can ship even before the deadline! There is not a single customer that will say no to reducing time to market!
So I’d say, yes – the Best Product is good enough.
And that’s how it’s done. I hope
How about your products? Do you work this way? Are your experiences similar? Share!
Thanks,
Assaf.
Demystifying Agile
Understanding the mechanics of Scrum is easy; otherwise there’s no way they could be taught in 16 hours, in a Certified Scrum Master class. Understanding why the mechanics work is a different thing altogether. In this series of posts, I will attempt to explain how and why they work the way they do; I firmly believe that attempting to use the mechanics of scrum without understanding the Agile spirit is a recipe for failure. I hope you enjoy the series.
Table of Contents:
- How to Manage a Self Managing Team
- Agile Contracts: Unveiling the Trick to Happy Customers
- Agile Tips & Tricks: How to Solve Real Issues with Scrum
Bookmark this page! More posts to come…